United States Coast Guard Motor Relocation
Matthew Clifford, Digging & Rigging, Inc.
Downers Grove North High School
Brent Genseke, Area Erectors Inc.
Oak Brook Commons
Riley Pettrone, La Grange Crane Service
Pharmaceutical Sand Filter Placement
Trapper Wyman, Mansfield Crane Service
Crawford Station Demo
Michael Havlicek, Stevenson Crane Service Inc.

Downers Grove North High School

Brent Genseke, Area Erectors Inc.

Wight Construction - Downers Grove North High School

In this lift plan we are setting a shop assembled truss over an existing/addition walkway, inside a courtyard, on top of new steel. The truss dimensions are 15’-2” wide by 60’-8” long and it weighed in at 4,527# not counting the block and rigging. This was not a heavy lift by any means, but crane access, transportation of the truss to the site, and rotating the truss once off loaded added some degrees of difficulty to the lift.

Crane placement on this project was limited due to underground hazards and the ability to keep other trades working. On a prior site visit we were able to estimate a possible location and to compile the dimensions needed i n order to generate an accurate representation of the jobsite in 3D Lift Plan. Our crane vendor also brought a unique tool to the table, a drone. Using their drone we were able to get a true birds eye view of the site as i t stood and import that image into the lift plan. This gave the general contractor and the school district the ability to see the current jobsite on the lift plan submitted. Between the images used, the documents generated, and a site walk they could then easily make the correlation between the drawing and the site.

Starting off the lift, there was the difficulty in getting the shop assembled trusses to the site. The jobsite is in the middle of a residential area and streets are narrow. Trying to navigate the access for the semi and extended trailer while the truss was on the trailer took some precision driving by the hauler. Patience, a couple of spotters, and a skilled driver and we were able to overcome the logistics of getting the piece to the site. Once we had the piece within reach of the crane we were able to really start the critical aspects of the lift.

Wight Construction - Downers Grove North High School

The truss was fabricated and loaded on the truck upside down. So once the truss was on site we had to offload the truss, stand it up, and then lay it over in order to rig it for setting. The standing up and rolling over process was reviewed with the crane rental company and the operator tasked with the job was on point. The truss rolled up and was laid over very smoothly and almost effortlessly. Without quality operators and equipment, lifts like this are even more difficult.

Truss stood up, rolled over, and now it is time to hoist. Prior to all that, we had to size the crane. Looking at the access, the truss weight, and additional constraints we were trying to thread a needle to make it all work. Through the planning process we were working with Nichols Crane Rental out of Joliet IL. Nichols had been on the job a couple of times and were familiar with access and restrictions to the site. The site had a strict no machinery before 8am rule due to the residential area literally on the other side of the fence. Nichols was able to provide the Liebherr LTM 1130 5.1 with jib to do the work. Outrigger placement, centerpin location, and tail swing were all taken into account in order to get the crane set up in the exact location planned. The crane was built in the precise location needed to uphold the accuracy of the lift plan.

Throughout the process 3D Lift Plan gave us the ability to bring as much information as possible to the table. Crane capacity, crane l ocation, and the 3D ability to see clearances all on a couple documents made the general contractor and school confident in our ability to complete the work in a safe manner. The lift went off as planned and we were able to keep the project on track. 3D Lift Planning the work, and working the 3D Lift Plan helped keep everything on track. In closing, credit for the work in the end goes to the operators and ironworkers that suit up each day to work safely.

At Area Erectors, we use 3D Lift Plan for a myriad of uses in planning our work. We will use it in the planning stage to size a crane. We will use it once we have a job in order to layout crane locations for different stages of construction. Lastly we use it once we have fabrication drawings to finalize a lift plan and convey to our field team what we were looking at prior to boots on the ground. This project i nvolved using 3D Lift Plan on multiple occasions where unique situations were encountered.

Jobsite Photos

Wight Construction - Downers Grove North High School Wight Construction - Downers Grove North High School Wight Construction - Downers Grove North High School Wight Construction - Downers Grove North High School Wight Construction - Downers Grove North High School Wight Construction - Downers Grove North High School Wight Construction - Downers Grove North High School Wight Construction - Downers Grove North High School Wight Construction - Downers Grove North High School Wight Construction - Downers Grove North High School Wight Construction - Downers Grove North High School Wight Construction - Downers Grove North High School Wight Construction - Downers Grove North High School Wight Construction - Downers Grove North High School Wight Construction - Downers Grove North High School